Check List for Cable Document Ref. No. 2.4
Contractor: Client:
Project: Location:
Supplier/Vendor:
Reference Drawing no:
Check List (Please tick mark in appropriate column)
Check Points Observations
Contactor/ Vendor Client
Storage & Handling
Check that Cables drums are stored on a well-drained hard surface, preferably on concrete, such that drums do not sink into the ground, causing rot & damage to cable drum(Especially for receipt of cables during monsoon)
Ensure ends of the cables are properly sealed to prevent ingress / absorption of moisture
Shelter the cables from rain and sun
Ensure that drums are resting on flanges and not on flat sides
Ensure drums are rolled across only in the direction of the arrow marked on the drum
Do not push the cable drums down the truck, use crane or roll down using suitable ramps
Use proper cable jacks to unleash cable from drum
Use cable rollers to pull the cables
Type Test - Certificates to be Submitted
Rated withstand AC voltage test
Partial discharge test
Rated withstand surge voltage test
Continuous AC voltage test with cyclic current loads (Number of heating cycles -3,)
Partial Discharge Test
Continues AC voltage Test with cyclic current (Number of Heating cycles-60)
Thermal Short Circuit Test
Continuous AC Voltage Test with cyclic current load. (Number of heating Cycles-63)
Rated withstand Surge Voltage Test
DC Voltage Test
Dynamic short circuit Test
Underground Cabling
Before laying of cables check the coordinated routing drgs with other services for crossing/spacing with any other underground / overhead service lines
Ensure that cable runs are truly horizontal, vertical or sloped with proper spacing between cables
Ensuring laying of Cables of correct size and specification
Check that there is no mechanical damage to insulation /armour / core
Check cable Megger values (500V megger for 1.1 KV and 2500/5000V for higher valves)
Ensure that no sharp turns / bends are given in cable route
Ensure proper approved depth of cable trench
Ensure provision of proper bricks / sand bedding
Finalize Joint location (if allowed & provided) & ensure these are strictly followed on site
Check that Cable route markers are provided at appropriate Distance
Check that there is no interference with low voltage installations (Min 600mm spacing)
Ensure that proper cable lugs / glands / shrouds of specified size and make are used
Check that HI-POT test is carried out
Check that sufficient loops are kept at supply & feeder end
Testing
Continuity test
Absence of cross phasing
Insulation resistance to
Earth / Sheath / Armour
Insulation resistance between conductors
Overhead Cabling
Before laying of cables check the coordinated routing drgs with other services for crossing/spacing with any other underground / overhead service lines
Ensure that cable runs are truly horizontal, vertical or sloped with proper spacing between cable to cable
Ensuring laying of Cables of correct size and specification
Check that there is no mechanical damage to insulation /armour / core
Check cable Megger values (500V megger for 1.1 KV and 2500/5000V for higher valves)
Ensure that no sharp turns / bends are given in cable route
Check that Cable trays are properly supported at different locations
Check that there are no sharp edges on cable trays
Finalize Joint location (if allowed & provided) & ensure these are strictly followed on site
Check for Painting of cable trays (at least two coats of red oxide)
Ensure that proper cable lugs / glands / shrouds of specified size and make are used
Check that HI-POT test is carried out
Check that sufficient loops are kept at supply & feeder end
Testing
Continuity test
Absence of cross phasing
Insulation resistance to
Earth / Sheath / Armour
Insulation resistance between conductors
General remarks, if any

 

 

 

Checked by:____________________________ (Site Engineer) Signature:

Date :

Review and approval by: CM/ PM

Sponsored

PD Consulting Engineers Pvt. Ltd. Transforming construction for a new generation "Cost, Quality & Project management"

QS & Cost management, Bill Checking / Audit, Technical Auditors, Valuation, Contract and Tendering, Project Management, Project Planning, Quality Control, Consulting Engineers, Structural Consultancy

Close


Comment:

Name:

Email:

Civil N Construction Blog



Relevant Topics

Check list for painting

Check List For Toitet Fixtures

Check List For Structural Steel Work

Check list for aluminium and glazing work

Check list for carpets and vinyl flooring

Check list for flush door shutter

Check list for framework for gypsum ceiling

Check list for framework for partition

Check list for grid ceiling

Check list for gypsum ceiling

Check list for laminating and veneering

Check list for metal door frames

Check list for skinning-for-partition

Check list for timber-door-window-ventilator

Check list for waterproofing

Check list for woodwn-door-window-ventilator-frames

Check list for work-station-and-loose-furniture

Check list for cement concrete flooring IPS

Check list for ACC block masonry

Check list for brick-masonry

Check list for concreting

Check list for kota stone flooring

Check list for plastering

Check list for polythene membrane under floor

Check list for pre concreting

Check list for terrazzo flooring

Check list for wall cladding and flooring

Check list for aluminium formwork

Check list for earth filling

Check list for excavation

Check list for PCC

Check list for piling-work

Check list for reinforcement

Check list for shuttering and propping

Checklist for site survey

Method statement for brick work

Method statement for concrete work

Method statement for installation of wooden door frame work

Method statement for plaster-work

Method statement for reinforcement work

Method statement for stone-work (wall- cladding)

Method statement for stone work(marble - granite)

Method statement for tile work

Method statement for backfilling & compaction

Method statement for formwork

Method statement for mass excavation

Method statement for shoring

P & M Deployment Release Schedule

Planning Controlling Purpose Advantage Planning Helps To Avoid

Planning Personnel Responsibilities

Check List For Main Distribution Board

Check List For Cooling Tower

Check List For Pipework & Sprinklers

Check List For Expansion Tank

Check List For Ducting Work

Check List For Condenser Water Pump

Check List For Transformer

Check List For Battery & Battery Charger

Check List For High Voltage Switchgear Lt Panel

Check List For Fan Coil Unit (fcu)

Check List For Cable

Check List For Motor

Check List For Chiller

Check List For Earthing

Check List For Circuit Breakers

Check List For Conduiting & Wiring

Check List For Current Transformer

Check List For Pumps

Check List For High Voltage Switchgear HT Panel

Check List For Control Panel

Check List For HVAC Fans

Check List For Secondary Chilled Water Pump

Check List For Primary Chilled Water Pump

Check List For Busduct

Check List For Hvac Piping Works

Check List For Distribution Board

Sponsored

PD Consulting Engineers Pvt. Ltd. Transforming construction for a new generation "Cost, Quality & Project management"

QS & Cost management, Bill Checking / Audit, Technical Auditors, Valuation, Contract and Tendering, Project Management, Project Planning, Quality Control, Consulting Engineers, Structural Consultancy

Close