Check List for Pipe work & Sprinklers

Er. Parbhakar Dwivedi
0
 

       

Check List for Pipe work & Sprinklers Document Ref. No. 4.2
Contractor: Client:
Project: Location:
Supplier/Vendor:
Reference Drawing no:
Check List (Please tick mark in appropriate column)
Check Points Observations
Contactor/ Vendor Client
I. Pre - Installation
Materials supplied confirm to specifications
Pipes and fittings are free from damage and clean internally and externally
Carry out random checks on welds and / or screwed joints for Prefabricated pipe work
Necessary certification for materials and welding of prefabricated pipe work is available prior to installation.
Necessary 'V' groves are made before welding of pipes(above 50mm Diameter
Carry out dimensional check on fabricated pipe work spools
One Coat of Red Oxide Primer
II. Installation
Pipe Routing & Cutouts
Hanger / Supports / Screws / Bolts / Nuts
Acoustic pads
Available space for fire sealants
Supports are fixed at the correct intervals
All pipe runs for correct falls / levels
7. Check services are installed to allow sufficient space for thermal insulation
8. Check that all bolts, nuts, hemispherical/ flat washers are fitted correctly with correct bolt lengths & Check protection of exposed threaded parts (Greasing & Capping)
All screwed joints are cleaned
Horizontal and vertical alignment for line equipment
Horizontal and vertical alignment of pipe work
All Painting is as per specification
All vents & drains are fitted Where required
All in line equipment including valves, etc. are correctly fitted as shown on construction drawings
Anchors / guides are properly located as shown on construction drawings and are securely fixed
Terminal connections are made and plugs /blank flanges / caps are fitted where necessary
Brackets are properly supporting pipe work
All bolts and nuts are tightened correctly
Correct flanges / gaskets are installed compatible with line service
Installed pipe work complies with line specification and drawing
All terminal connections are piped in correct relation to flows
Facilities are built in systems for flushing as shown on construction drawings
All doors and cabinets open fully and that hose reels rotate through 180 degrees
III. Testing
Services for damage
All services to ensure all open ends are properly capped off
Valves are left in open position
Stool pieces where required are fitted to temporarily replace valves and other inline equipment
Regulating and non-return valves are installed to correct orientation
Pressures & carry out pressure testing
CI pipes tested with water before installation and after installation it should be tested with Smoke
Hose reel automatic valves release water when reel is unwound to a predetermined length not in excess of 3.25m
Carry out water test on all services with exception of the dry riser system
Complete systems are demonstrated and tested in the presence of and to the satisfaction of the Fire Authority
IV. Post Testing / Pre - Commissioning
All inline equipment are properly fitted
All sprinklers are correctly located & coordinated with ceiling / lights / grills
Test points are correctly installed and clear of insulation
All control valves are operable and orientation is correct
All isolating / regulating valves are operable and orientation is correct
All probes, Pressure gauges and test points are fitted at correct locations as shown on construction drawings
System has been pressure tested and in a condition to satisfy the requirements of the specification
Earth bonding has been completed where applicable
Arrow indicates the Supply/Return Direction of Fluid Flow
Operation instruction plates clearly indicate the method of use of the hose reels and is installed adjacent to all reels
General remarks, if any

 

 

 

Checked by:____________________________ (Site Engineer) Signature:

Date :

Review and approval by: CM/ PM

Sponsored

PD Consulting Engineers Pvt. Ltd. Transforming construction for a new generation "Cost, Quality & Project management"

QS & Cost management, Bill Checking / Audit, Technical Auditors, Valuation, Contract and Tendering, Project Management, Project Planning, Quality Control, Consulting Engineers, Structural Consultancy

Close


Comment:

Name:

Email:

Civil N Construction Blog



Relevant Topics

Check list for painting

Check List For Toitet Fixtures

Check List For Structural Steel Work

Check list for aluminium and glazing work

Check list for carpets and vinyl flooring

Check list for flush door shutter

Check list for framework for gypsum ceiling

Check list for framework for partition

Check list for grid ceiling

Check list for gypsum ceiling

Check list for laminating and veneering

Check list for metal door frames

Check list for skinning-for-partition

Check list for timber-door-window-ventilator

Check list for waterproofing

Check list for woodwn-door-window-ventilator-frames

Check list for work-station-and-loose-furniture

Check list for cement concrete flooring IPS

Check list for ACC block masonry

Check list for brick-masonry

Check list for concreting

Check list for kota stone flooring

Check list for plastering

Check list for polythene membrane under floor

Check list for pre concreting

Check list for terrazzo flooring

Check list for wall cladding and flooring

Check list for aluminium formwork

Check list for earth filling

Check list for excavation

Check list for PCC

Check list for piling-work

Check list for reinforcement

Check list for shuttering and propping

Checklist for site survey

Method statement for brick work

Method statement for concrete work

Method statement for installation of wooden door frame work

Method statement for plaster-work

Method statement for reinforcement work

Method statement for stone-work (wall- cladding)

Method statement for stone work(marble - granite)

Method statement for tile work

Method statement for backfilling & compaction

Method statement for formwork

Method statement for mass excavation

Method statement for shoring

P & M Deployment Release Schedule

Planning Controlling Purpose Advantage Planning Helps To Avoid

Planning Personnel Responsibilities

Check List For Main Distribution Board

Check List For Cooling Tower

Check List For Pipework & Sprinklers

Check List For Expansion Tank

Check List For Ducting Work

Check List For Condenser Water Pump

Check List For Transformer

Check List For Battery & Battery Charger

Check List For High Voltage Switchgear Lt Panel

Check List For Fan Coil Unit (fcu)

Check List For Cable

Check List For Motor

Check List For Chiller

Check List For Earthing

Check List For Circuit Breakers

Check List For Conduiting & Wiring

Check List For Current Transformer

Check List For Pumps

Check List For High Voltage Switchgear HT Panel

Check List For Control Panel

Check List For HVAC Fans

Check List For Secondary Chilled Water Pump

Check List For Primary Chilled Water Pump

Check List For Busduct

Check List For Hvac Piping Works

Check List For Distribution Board