METHOD STATEMENT FOR WOODEN DOOR(FREAME WORK)

Er. Parbhakar Dwivedi
0
 

       

Reference

The following reference shall be used in conjunction with this procedure

  • Technical Specifications
  • IS Codes
  • Drawings
  • BOQ

Resources Used

A. Manpower

  • Skilled Labour(Carpenter)
  • Unskilled Labour

Safety Points

  • All workers are in PPEs.

Work Procedure

  • Timber for door, window and ventilators frames shall be as specified. Timber shall be sawn in the direction of the grains. All members of a frame shall be of the same species of timber and shall be straight without any warp or bow. Frames shall have smooth, well-planned (wrought) surfaces except the surfaces touching the walls, lintels, sill etc., which may be left clean sawn. Rebates, rounding or moulding shall be done before the members are jointed into frames. The depth of the rebate shall be as per Drawing and specification.
  • A tolerance of ┬▒ 2 mm shall be permitted in the specified finished dimensions of timber sections in frames.
  • Fixing of Frames: The frames shall be got approved by the Engineer-in-Charge before being painted, oiled or otherwise treated and before fixing in position. The surface of the frames abutting masonry or concrete and the portions of the frames embedded in floors shall be given a coating of coal tar.
  • Frames shall be fixed to the abutting masonry or concrete with metallic fasteners as specified

Precautions

  • A minimum of three metallic fastener shall be fixed on each side of door and window frames one at centre point and other two at 30 cm from the top and bottom of the frames. In case of window and ventilator frames of less than 1 m in height two hold fasts shall be fixed on each side at quarter point of the frames.

Sponsored

PD Consulting Engineers Pvt. Ltd. Transforming construction for a new generation "Cost, Quality & Project management"

QS & Cost management, Bill Checking / Audit, Technical Auditors, Valuation, Contract and Tendering, Project Management, Project Planning, Quality Control, Consulting Engineers, Structural Consultancy

Close


Comment:

Name:

Email:

Civil N Construction Blog



Relevant Topics

Check list for painting

Check List For Toitet Fixtures

Check List For Structural Steel Work

Check list for aluminium and glazing work

Check list for carpets and vinyl flooring

Check list for flush door shutter

Check list for framework for gypsum ceiling

Check list for framework for partition

Check list for grid ceiling

Check list for gypsum ceiling

Check list for laminating and veneering

Check list for metal door frames

Check list for skinning-for-partition

Check list for timber-door-window-ventilator

Check list for waterproofing

Check list for woodwn-door-window-ventilator-frames

Check list for work-station-and-loose-furniture

Check list for cement concrete flooring IPS

Check list for ACC block masonry

Check list for brick-masonry

Check list for concreting

Check list for kota stone flooring

Check list for plastering

Check list for polythene membrane under floor

Check list for pre concreting

Check list for terrazzo flooring

Check list for wall cladding and flooring

Check list for aluminium formwork

Check list for earth filling

Check list for excavation

Check list for PCC

Check list for piling-work

Check list for reinforcement

Check list for shuttering and propping

Checklist for site survey

Method statement for brick work

Method statement for concrete work

Method statement for installation of wooden door frame work

Method statement for plaster-work

Method statement for reinforcement work

Method statement for stone-work (wall- cladding)

Method statement for stone work(marble - granite)

Method statement for tile work

Method statement for backfilling & compaction

Method statement for formwork

Method statement for mass excavation

Method statement for shoring

P & M Deployment Release Schedule

Planning Controlling Purpose Advantage Planning Helps To Avoid

Planning Personnel Responsibilities

Check List For Main Distribution Board

Check List For Cooling Tower

Check List For Pipework & Sprinklers

Check List For Expansion Tank

Check List For Ducting Work

Check List For Condenser Water Pump

Check List For Transformer

Check List For Battery & Battery Charger

Check List For High Voltage Switchgear Lt Panel

Check List For Fan Coil Unit (fcu)

Check List For Cable

Check List For Motor

Check List For Chiller

Check List For Earthing

Check List For Circuit Breakers

Check List For Conduiting & Wiring

Check List For Current Transformer

Check List For Pumps

Check List For High Voltage Switchgear HT Panel

Check List For Control Panel

Check List For HVAC Fans

Check List For Secondary Chilled Water Pump

Check List For Primary Chilled Water Pump

Check List For Busduct

Check List For Hvac Piping Works

Check List For Distribution Board

Sponsored

PD Consulting Engineers Pvt. Ltd. Transforming construction for a new generation "Cost, Quality & Project management"

QS & Cost management, Bill Checking / Audit, Technical Auditors, Valuation, Contract and Tendering, Project Management, Project Planning, Quality Control, Consulting Engineers, Structural Consultancy

Close