METHOD STATEMENT FOR MASS EXCAVATION

Er. Parbhakar Dwivedi
0
 

       

Reference:

The following reference shall be used in conjunction with this procedure

  • Technical Specifications
  • Drawings
  • BOQ
  • Soil Investigation Report

Resources used

A. Manpower

  • Skilled Labour
  • Unskilled Labour

B. Machinery

  • Excavator (Poclain)
  • Backhoe (JCB)
  • Dumper

Safety Points

  • Permits
  • Traffic management
  • Shoring
  • Safe slopes
  • Fencing
  • Warning signs
  • Basement level of adjacent building

Work procedure

Setting Out

  • A temporary bench mark (TBM) to be established
  • The ground levels shall be taken at 5 to 10 meter intervals in uniformly sloping ground and at closer intervals where local mounds, pits or undulations are met with.

Marking of plan size of likely excavation pit

  • Mark on ground area to be excavated including working space margin & slope stabilization.

Excavation Procedure:

  • Top soil (300mm) to be retained within the premises as per LEED require, if any.
  • If practicable, to retain soil as much as possible for backfilling at a later date to avoid extra expenditure.
  • To Plan the excavating quantity of soil with in the scheduled time. Machinery has to be deployed as per the requirement.
  • Logistic schedule has prepared the quantity of soil to be excavated from the buildings footprint and working areas every day for the excavation period. Transportation of the bulk material has been assumed per truck basis, i.e. how many truck moves out of the site are required.
  • Excavation shall be undertaken to the width of the Basement/Retaining wall footing including necessary margins for construction operation as per drawing or directed otherwise. Where the nature of soil or the depth of the trench and season of the year, do not permit vertical sides, it shall put up the necessary shoring, strutting and planking or cut slopes with or without steps, to a safer angle.
  • If practicable, stock soil quantity required later for backfilling around foundation which shall be dumped as specified above.
  • In the area where works are under execution water table low enough so as not to cause any harm to the work like pumping out or bailing out water, if required, this will include water coming from any source, such as rains, accumulated rain water, floods, leakages from sewer and water mains, subsoil water table being high or due to any other cause whatsoever. It shall make necessary provision of pumping(of adequate Capacity), dredging bailing out water coming from all above sources and excavation and other works shall be kept free of water by providing suitable system approved by the Engineer-in-charge.
  • The water level is likely to rise up to 1 to 2 m. during rainy season. In order to avoid possibility of basement floor of main building being getting uplifted/damaged due to water pressure, shall lower the ground water table below the proposed foundation level by boring tube wells all around the proposed building using well point sinking method or any suitable method as approved by Engineer-in-charge. Sub soil water table shall be maintained at least 50 cm. below the P.C.C. level during laying of P.C.C. water proofing treatment, laying of basement raft and beams including filling of earth/sand under the basement floor. The water table shall not be allowed to rise above base of raft level until completion of outer retaining walls including water proofing of vertical surface of walls and back filling along the walls upto ground level and until the structure attains such height to counter balance the uplift pressure.
  • Continue excavation with excavator till about 30 cm above final excavation level. Excavate dress and level this last portion manually.
  • When final level of excavation is reached light mechanical compactor will be used with sprinkling of water where excavation is dry to have a compacted top surface of excavation for further work to proceed.
  • Any loose or soft bed encountered in excavation at the required depth, shall be excavated to a firm bed and difference made upto the required level with PCC or shall be compacted and tested to 95% of MDD.
  • The shoring and strutting of the sides to withhold the face of excavation pits/trenches shall be done as approved from safety points of view.
  • Final excavated levels of the foundations shall be recorded.
  • Area shall be suitable barricading with suitably painted of GI. Sheets or as specified.

Precautions

  • Adequate protective measures shall be taken to see that the excavation operations do not damage the adjoining structures or dislocate the services. Water supply pipes, sluice valve chambers, sewerage pipes, manholes, drainage pipes and chambers, communication cables, power supply cables etc. met with in the course of excavation shall be properly supported and adequately protected, so that these services remain functional.
  • Excavation shall not be carried out below the foundation level of the adjacent buildings until underpinning, shoring etc.

Sponsored

PD Consulting Engineers Pvt. Ltd. Transforming construction for a new generation "Cost, Quality & Project management"

QS & Cost management, Bill Checking / Audit, Technical Auditors, Valuation, Contract and Tendering, Project Management, Project Planning, Quality Control, Consulting Engineers, Structural Consultancy

Close


Comment:

Name:

Email:

Civil N Construction Blog



Relevant Topics

Check list for painting

Check List For Toitet Fixtures

Check List For Structural Steel Work

Check list for aluminium and glazing work

Check list for carpets and vinyl flooring

Check list for flush door shutter

Check list for framework for gypsum ceiling

Check list for framework for partition

Check list for grid ceiling

Check list for gypsum ceiling

Check list for laminating and veneering

Check list for metal door frames

Check list for skinning-for-partition

Check list for timber-door-window-ventilator

Check list for waterproofing

Check list for woodwn-door-window-ventilator-frames

Check list for work-station-and-loose-furniture

Check list for cement concrete flooring IPS

Check list for ACC block masonry

Check list for brick-masonry

Check list for concreting

Check list for kota stone flooring

Check list for plastering

Check list for polythene membrane under floor

Check list for pre concreting

Check list for terrazzo flooring

Check list for wall cladding and flooring

Check list for aluminium formwork

Check list for earth filling

Check list for excavation

Check list for PCC

Check list for piling-work

Check list for reinforcement

Check list for shuttering and propping

Checklist for site survey

Method statement for brick work

Method statement for concrete work

Method statement for installation of wooden door frame work

Method statement for plaster-work

Method statement for reinforcement work

Method statement for stone-work (wall- cladding)

Method statement for stone work(marble - granite)

Method statement for tile work

Method statement for backfilling & compaction

Method statement for formwork

Method statement for mass excavation

Method statement for shoring

P & M Deployment Release Schedule

Planning Controlling Purpose Advantage Planning Helps To Avoid

Planning Personnel Responsibilities

Check List For Main Distribution Board

Check List For Cooling Tower

Check List For Pipework & Sprinklers

Check List For Expansion Tank

Check List For Ducting Work

Check List For Condenser Water Pump

Check List For Transformer

Check List For Battery & Battery Charger

Check List For High Voltage Switchgear Lt Panel

Check List For Fan Coil Unit (fcu)

Check List For Cable

Check List For Motor

Check List For Chiller

Check List For Earthing

Check List For Circuit Breakers

Check List For Conduiting & Wiring

Check List For Current Transformer

Check List For Pumps

Check List For High Voltage Switchgear HT Panel

Check List For Control Panel

Check List For HVAC Fans

Check List For Secondary Chilled Water Pump

Check List For Primary Chilled Water Pump

Check List For Busduct

Check List For Hvac Piping Works

Check List For Distribution Board

Sponsored

PD Consulting Engineers Pvt. Ltd. Transforming construction for a new generation "Cost, Quality & Project management"

QS & Cost management, Bill Checking / Audit, Technical Auditors, Valuation, Contract and Tendering, Project Management, Project Planning, Quality Control, Consulting Engineers, Structural Consultancy

Close