METHOD STATEMENT FOR STONE WORK(WALL CLADDING)

Er. Parbhakar Dwivedi
0
 

       

Reference

The following reference shall be used in conjunction with this procedure

  • Technical Specifications
  • IS Codes
  • Drawings
  • BOQ

Resources Used

A. Manpower

  • Skilled Labour(Mason Gang)
  • Unskilled Labour

B. Machinery

  • Stone cutters,
  • Spirit levels,
  • solid notch trowel
  • Hammers etc. as applicable

Safety Points

  • While doing job at height, person must anchor his safety belt with "LIFELINE"
  • All workers are in PPEs.

Work Procedure

  • Stone shall be hard, sound durable and tough free from cracks, decay and weathering and defects like cavities cracks, flaws, holes, veins, patches of soft or loose materials etc. Thickness of stone shall be as specification.
  • Stone shall be cut with the gang saw to the required size and shape on all beds and joints so as to free from any waviness and to give truly vertical horizontal surface as required. The exposed face and sides of stones forming joints shall be such that the straight edge laid along the face of the stone is in contact with every point on it. All the visible angle and edges shall be square and free from chipping. The dressed stone shall be of the thickness specified with permissible tolerance of + 2 mm.
  • Fixing- The size & shape of the cramps shall be as per drawing and as per directions of Engineer- in-charge. The samples of steel cramps should be approved in advance before starting the stone cladding work. The cramp shall be attached to top and bottom of the stone. The cramps shall have inbuilt adjustment for vertical and horizontal alignment.
  • The cramps used to hold support and transfer the load of stone unit to the supporting structured steels as per the design. Approval of the same shall be obtained from the Engineer- in-Charge.
  • The minimum number of clamps required shall be as per requirement of design to carry the load of individual stone slabs. The cramps shall be spaced not more than 60 cm horizontally and vertically along the stone side for insertion of pins / bolt attached with the steel cramps. Adequate cutting in stone shall be made with precision instrument to hold the cramps pins at the joints.
  • Stone shall be secured with clamps with high quality workmanship. The walls shall be carried up truly plumb. All the courses shall be laid truly horizontal and all the vertical joints truly vertical.
  • Jointing: Joints horizontal and vertical shall be filled with weather sealant of make as approved by Engineer-in-charge with the help of pouring gun for filling the sealant. Before filling the joint with sealant, masking tape are required to be fixed on stones surface on both edges of joints of the stones, so that sealant may not spoil the surface of the stone. When all the joints are filled and sealant has dried, the masking tape may be removed.

Precautions:

  • The work shall also be suitably protected from damage.

Sponsored

PD Consulting Engineers Pvt. Ltd. Transforming construction for a new generation "Cost, Quality & Project management"

QS & Cost management, Bill Checking / Audit, Technical Auditors, Valuation, Contract and Tendering, Project Management, Project Planning, Quality Control, Consulting Engineers, Structural Consultancy

Close


Comment:

Name:

Email:

Civil N Construction Blog



Relevant Topics

Check list for painting

Check List For Toitet Fixtures

Check List For Structural Steel Work

Check list for aluminium and glazing work

Check list for carpets and vinyl flooring

Check list for flush door shutter

Check list for framework for gypsum ceiling

Check list for framework for partition

Check list for grid ceiling

Check list for gypsum ceiling

Check list for laminating and veneering

Check list for metal door frames

Check list for skinning-for-partition

Check list for timber-door-window-ventilator

Check list for waterproofing

Check list for woodwn-door-window-ventilator-frames

Check list for work-station-and-loose-furniture

Check list for cement concrete flooring IPS

Check list for ACC block masonry

Check list for brick-masonry

Check list for concreting

Check list for kota stone flooring

Check list for plastering

Check list for polythene membrane under floor

Check list for pre concreting

Check list for terrazzo flooring

Check list for wall cladding and flooring

Check list for aluminium formwork

Check list for earth filling

Check list for excavation

Check list for PCC

Check list for piling-work

Check list for reinforcement

Check list for shuttering and propping

Checklist for site survey

Method statement for brick work

Method statement for concrete work

Method statement for installation of wooden door frame work

Method statement for plaster-work

Method statement for reinforcement work

Method statement for stone-work (wall- cladding)

Method statement for stone work(marble - granite)

Method statement for tile work

Method statement for backfilling & compaction

Method statement for formwork

Method statement for mass excavation

Method statement for shoring

P & M Deployment Release Schedule

Planning Controlling Purpose Advantage Planning Helps To Avoid

Planning Personnel Responsibilities

Check List For Main Distribution Board

Check List For Cooling Tower

Check List For Pipework & Sprinklers

Check List For Expansion Tank

Check List For Ducting Work

Check List For Condenser Water Pump

Check List For Transformer

Check List For Battery & Battery Charger

Check List For High Voltage Switchgear Lt Panel

Check List For Fan Coil Unit (fcu)

Check List For Cable

Check List For Motor

Check List For Chiller

Check List For Earthing

Check List For Circuit Breakers

Check List For Conduiting & Wiring

Check List For Current Transformer

Check List For Pumps

Check List For High Voltage Switchgear HT Panel

Check List For Control Panel

Check List For HVAC Fans

Check List For Secondary Chilled Water Pump

Check List For Primary Chilled Water Pump

Check List For Busduct

Check List For Hvac Piping Works

Check List For Distribution Board

Sponsored

PD Consulting Engineers Pvt. Ltd. Transforming construction for a new generation "Cost, Quality & Project management"

QS & Cost management, Bill Checking / Audit, Technical Auditors, Valuation, Contract and Tendering, Project Management, Project Planning, Quality Control, Consulting Engineers, Structural Consultancy

Close