METHOD STATEMENT FOR TILE WORK

Er. Parbhakar Dwivedi
0
 

       

Reference

The following reference shall be used in conjunction with this procedure

  • Technical Specifications
  • IS Codes
  • Drawings
  • BOQ

Resources Used

A. Manpower

  • Skilled Labour(Mason Gang)
  • Unskilled Labour

B. Machinery

  • Tile cutters,
  • Spirit levels,
  • Tile edge nippers,
  • Masonry nails,
  • Hammers

Safety Points

  • While doing job at height, person must anchor his safety belt with "LIFELINE"
  • Provide safety cages around moving motors
  • All workers are in PPEs.

Work Procedure

Carry out setting out of wall and floor tiling as below:

Floor Tiling

  • Establish a datum level for finished floor.
  • Control overall finished floor level by a series of spot levels.
  • Set out tiling from center of the room in straight lines parallel to the axis of the room.
  • Align the floor tile joints with the joints on skirting tiles.

Wall Tiling

  • Fix tiles from the highest level of the wall and work downwards to the floor.
  • Place the tiles with consistent joint width and ensure the horizontal and vertical joints are parallel.

Procedure

  • Dampen the wall / floor surface to be tiled.
  • Soak the tiles in clean water for minimum 2 hours before laying.
  • Remove the tiles from water and stack them together with the end tiles face outwards to drain away excessive water before laying the tiles.
  • Spread mortar / adhesive uniformly over the back of each tile to a thickness as per specifications.
  • Over this mortar bedding neat grey cement slurry of honey like consistency shall be spread at the rate of 3.3 kg of cement per square metre over an area up to one square metre
  • Lay the tiles on to the floor / wall. Adjust the position and press firmly to the floor / wall.
  • Brush off loose mortar and wash mortar stains on the tiles with clean water. Remove excessive water with dry cloth.
  • Use a long ruler and check the level of the tiles. Also check the width and straightness of the joints. Ensure the floor tiles are laid to fall towards the floor trap.
  • Repeat the process until the whole floor / wall area is tiled.
  • For floor & wall tiles, fill the joints with grout according to Manufacturer’s recommendation.
  • The floor shall then be kept wet for 7 days.

Precautions:

  • Joints are aligned and consistent with skirting and wall tiles
  • Consistent Pointing.

No hollow sound when tapped the Tile.

Sponsored

PD Consulting Engineers Pvt. Ltd. Transforming construction for a new generation "Cost, Quality & Project management"

QS & Cost management, Bill Checking / Audit, Technical Auditors, Valuation, Contract and Tendering, Project Management, Project Planning, Quality Control, Consulting Engineers, Structural Consultancy

Close


Comment:

Name:

Email:

Civil N Construction Blog



Relevant Topics

Check list for painting

Check List For Toitet Fixtures

Check List For Structural Steel Work

Check list for aluminium and glazing work

Check list for carpets and vinyl flooring

Check list for flush door shutter

Check list for framework for gypsum ceiling

Check list for framework for partition

Check list for grid ceiling

Check list for gypsum ceiling

Check list for laminating and veneering

Check list for metal door frames

Check list for skinning-for-partition

Check list for timber-door-window-ventilator

Check list for waterproofing

Check list for woodwn-door-window-ventilator-frames

Check list for work-station-and-loose-furniture

Check list for cement concrete flooring IPS

Check list for ACC block masonry

Check list for brick-masonry

Check list for concreting

Check list for kota stone flooring

Check list for plastering

Check list for polythene membrane under floor

Check list for pre concreting

Check list for terrazzo flooring

Check list for wall cladding and flooring

Check list for aluminium formwork

Check list for earth filling

Check list for excavation

Check list for PCC

Check list for piling-work

Check list for reinforcement

Check list for shuttering and propping

Checklist for site survey

Method statement for brick work

Method statement for concrete work

Method statement for installation of wooden door frame work

Method statement for plaster-work

Method statement for reinforcement work

Method statement for stone-work (wall- cladding)

Method statement for stone work(marble - granite)

Method statement for tile work

Method statement for backfilling & compaction

Method statement for formwork

Method statement for mass excavation

Method statement for shoring

P & M Deployment Release Schedule

Planning Controlling Purpose Advantage Planning Helps To Avoid

Planning Personnel Responsibilities

Check List For Main Distribution Board

Check List For Cooling Tower

Check List For Pipework & Sprinklers

Check List For Expansion Tank

Check List For Ducting Work

Check List For Condenser Water Pump

Check List For Transformer

Check List For Battery & Battery Charger

Check List For High Voltage Switchgear Lt Panel

Check List For Fan Coil Unit (fcu)

Check List For Cable

Check List For Motor

Check List For Chiller

Check List For Earthing

Check List For Circuit Breakers

Check List For Conduiting & Wiring

Check List For Current Transformer

Check List For Pumps

Check List For High Voltage Switchgear HT Panel

Check List For Control Panel

Check List For HVAC Fans

Check List For Secondary Chilled Water Pump

Check List For Primary Chilled Water Pump

Check List For Busduct

Check List For Hvac Piping Works

Check List For Distribution Board

Sponsored

PD Consulting Engineers Pvt. Ltd. Transforming construction for a new generation "Cost, Quality & Project management"

QS & Cost management, Bill Checking / Audit, Technical Auditors, Valuation, Contract and Tendering, Project Management, Project Planning, Quality Control, Consulting Engineers, Structural Consultancy

Close