Sr. No. Description Unit Rate* Towers Rate* Basement & Misc. Qty. Towers A Qty. Towers B Qty. Basement & Misc. Amount
Note : All Basic Rate FOR Site, OPC Cement (Grey color) = Rs.240/Bag, Reinforcement (TMT ) or High yield strength Deformed (Tor steel) bars of all size including 6mm dia of Fe-500 grade - Rs 45000/MT, Structural Steel - Rs 50000/MT, Quoted Rates are for all heights, depths, levels, leads and lifts.
2.6 Precast concrete / Wall
2.6.1 Precast concrete
a. Providing, hoisting and fixing precast reinforced cement concrete work with M-20 grade concrete of any shape & thickness in trench covers, cills, copings, vertical supports of kitchen counters, expansion joint cover etc. where ever required including the cost of required centring, shuttering, making chamfered edges, grooves, drip course finishing smooth with 6mm thick cement plaster 1:3 (1 cement : 3 fine sand) on exposed surfaces making chamferd edges, grooves, drip course etc complete in all respect wherever shown but excluding cost of reinforcement, at all floors, for all heights, and at all depth etc. as per drawing and as directed by Engineer-in-charge (Reinforcement shall be paid separately in respective item) cum. 11600 11600
b. Providing and fixing precast cement concrete ( M -25 grade) drain cover panels, fixed to MS flat as shown in the drawing or as called complete in all respect (reinforcement steel will be measured and paid separately in respective item) cum 12200 12200
2.6.2 PRECAST SANDWICH WALL
(Rate includes all allied works for production and erection of element incl all accessories, consumables, grouting with approved grout all complete except cost of Cement, Reinforcement Steel which would be supplied by Owner free of cost however unloading/shifting etc is included in cost)
Production and erection of Precast Wall panels of overall thickness 150 mm having 50 mm thick XPS insulation material in between, with M40 Grade Concrete. Rate includes all material charges such as concrete, lifting inserts, connecting loop, cutting/bending & tying steel reinforcement (Fe500 Grade) and required Admixtures except material supplied by owner as free issue, also includes all labour charge for Placing of reinforcement, preparation of mould, pouring of concrete as per shop drawings, de-moulding, erection, all fixing arrangement, anchors, fasteners etc complete. ( Insulation material & Steel would be paid seperately) Volume of concrete only will be measured and paid. Cum 10200 10200
2.6.3 Providing & Fixing 50MM thick Sandwich Material (XPS Insulation material) as per specifications/HVAC requirement including all fixing arrangement with pins & accessories etc. complete in all respects as per manufacture specification, approved drawings complete in all respects. (Base Rate of material Rs 450 per sqm incl all taxes excluding) Sqm 535 535
2.7 Making holes
Making holes of required size and shape in post RCC work up to RCC depth of 500 mm at designated locations if not mentioned in the drawings but required by Engineer-in-charge including cutting of reinforcement and finishing edges smooth with 1:3 (1 cement : 3 coarse sand) cement mortar and plugging the open spaces around sleeves/ puddle flanges with concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20mm nominal size) mixed with waterproofing compound etc.of approved manufacture complete in all respect
2.6.1 Upto 0.5 sqm area Sqm 8500 8200
2.6.2 Above 0.5 sqm to 1 sqm area Sqm 8500 8200
2.6.3 Above 1 sqm area Sqm 8500 8200
2.8 Closing of cutouts
Closing of cut outs made in any RCC or Brickwork with Cement concrete of M25 grade or Cement mortar of 1 : 4 mix as required, including waterproofing compound , neat cement finish etc complete in all respect as directed.
a. For brick/ block masonry -upto a max. thickness of 300mm Sqm. 2500 2500
b. For RCC work - upto a max. thickness of 300mm Sqm. 4500 4500
2.9 Expansion fasteners
2.9.1 Supplying and fixing expansion fasteners including testing for fixing into already constructed structure (quoted rate to include design & testing of fasteners for its performance).
a. 8mm dia - standard length Each 90 90
b. 10mm dia - standard length Each 125 125
c. 12mm dia - standard length Each 175 175
2.9.2 Item same as 2.9.1 but using Chemical Resin Fasteners instead of expansion Fasteners (quoted rate to include design & testing of fasteners for its performance).
a. 8mm dia - standard length Each 172 172
b. 10mm dia - standard length Each 430 430
c. 12mm dia - standard length Each 650 650
2.10 Rebaring
Providing and fastening Rebar various diameters of TMT bars by Hilti with HIT - HY150 /FISCHER with FISV 360S chemical, as per structural drawing, manufactures instructions and as instructed by Engineer-In-Charge for anchoring of reinforcement bars. Rate to include cost of drilling by mechanical means in concrete, cleaning the drilled holes, insertion of Hilti HIT HY-150, placing rebar and allow adhesive to cure, complete in all respect as per details and directed by Engineer-In-Charge.
a 8 mm dia with 100 mm depth each 150 150
b 10 mm dia with 100 mm depth each 180 180
c 12 mm dia with 120 mm depth each 225 225
d 16 mm dia with 160 mm depth each 425 425
e 20 mm dia with 200 mm depth each 600 600
f 25 mm dia with 200 mm depth each 700 700
g 25 mm dia with 250 mm depth each 900 900
h 32 mm dia with 320 mm depth each 1200 1200
2.11 Core Cutting in RCC
Providing & making Core cutting of holes in RCC floors/Columns/Beams/Slabs/retaining walls etc.(including cutting of reinforcement bars/plates if any)making good by approved specialised agency, including all labour, machinery, tools, tackles , accessories etc strictly as per design & drawing requirement and as directed by Engineer-in-Charge.
a 50 mm dia upto 150 depth Each 160 160
b 50 mm dia upto 450 depth Each 310 310
c 80 mm dia upto 150 depth Each 230 230
d 80 mm dia upto 450 depth Each 403 403
e 100 mm dia upto 150 depth Each 300 300
f 100 mm dia upto 450 depth Each 750 750
g 150 mm dia upto 150 depth Each 400 400
h 150 mm dia upto 450 depth Each 1050 1050
i 200 mm dia upto 150 depth Each 500 500
j 200 mm dia upto 450 depth Each 1250 1250
k 250 mm dia upto 150 depth Each 650 650
l 250 mm dia upto 450 depth Each 1650 1650
2.12 Coupler / Reducer Coupler Each
Providing, Bar Threading and fixing tapered / parallel threaded couplers conforming to IS code :1786 including threading, enlargement at connection by forging, protecting the prepared reinforcement bars and related operations as required to complete the works per direction of Engineer-in-Charge. Coupling joint should be provided in staggered manner and should not at same location. (The length of the bars in which coupler is to be provided should not be less than 4 Meter.) Each
a. 16 mm Coupler Each 65 65
b 20 mm Coupler Each 86 86
c. 25 mm Coupler Each 117 117
d. 28 mm Coupler Each 147 147
e. 32 mm Coupler Each 173 173
f. 16 x 20 mm Reducer Coupler Each 83 83
g. 20 mm x 25 mm Reducer Coupler Each 112 112
h. 16 mm x 25 mm Reducer Coupler Each 110 110
i 25 mm x 32 mm Reducer Coupler Each 170 170
j 20 mm x 32 mm Reducer Coupler Each 167 167
k 16 mm x 32 mm Reducer Coupler Each 161 161
Total carried over to summary Each
* Average market rate but may vary with locality, class of contractor & client, material & resource availability, quality of material, time, quantity, local authority etc. and excluding service tax / GST etc.

Sponsored

PD Consulting Engineers Pvt. Ltd. Transforming construction for a new generation "Cost, Quality & Project management"

QS & Cost management, Bill Checking / Audit, Technical Auditors, Valuation, Contract and Tendering, Project Management, Project Planning, Quality Control, Consulting Engineers, Structural Consultancy

Close


Comment:

Name:

Email:

Sponsored

PD Consulting Engineers Pvt. Ltd. Transforming construction for a new generation "Cost, Quality & Project management"

QS & Cost management, Bill Checking / Audit, Technical Auditors, Valuation, Contract and Tendering, Project Management, Project Planning, Quality Control, Consulting Engineers, Structural Consultancy

Close