Quality Control Method Statement:

Method statement is needed to establish the various hold point (check point) and operation procedures to do the work of any activity in the field. The executing agency will collect all relevant data / information for carrying out the activity and will then prepare and submit work methodology.

The contractor would submit detailed method statement of each activity giving the quantum of activity, resources which he wants to deploy, time to be taken by the activity and the methods which he proposes to follow. It would be reviewed by the project manager and commented, if necessary. The contractor and project manager would designate key personnel responsible for each activity, who will coordinate while performing the activity.

Calibrated measuring devices will be used for checking and testing. Test results and measurements will be recorded in quality formats and product will be preserved till hand over. Areas of post hand over checks will be identified.

The activities of each type of work shall be grouped under three heads.

  • Pre-Construction Stage
  • Construction Stage
  • Post-Construction Stage

A. Pre- Construction Stage:

  1. Procurement and testing of materials.
  2. Mobilizing and checking serviceability of equipment and machine.
  3. Quality control aides and instruments.

B. Construction Stage:

This shall vary with the types of work and will cover quality checks during construction phase at required frequencies. Test to be done at site lab and outside labs will be identified. Proper documentation to show that tests required have been carried out and satisfy the laid down criteria, will be maintained.

C. Post- Construction Stage:

The activities (curing, de shuttering etc. finishing if required) will be checked on completion of construction activities. Testing and commissioning of installations will also be checked at this stage.

Sponsored

PD Consulting Engineers Pvt. Ltd. Transforming construction for a new generation "Cost, Quality & Project management"

QS & Cost management, Bill Checking / Audit, Technical Auditors, Valuation, Contract and Tendering, Project Management, Project Planning, Quality Control, Consulting Engineers, Structural Consultancy

Close


Comment:

Name:

Email:

Civil N Construction Blog



Relevant Topics

Tests for stones

Tests For Limestone

Tests Of Mortar

Specifications For Water (IS 456)

Determine Flexure Strength Of Concrete

Procedure For Test Of Silt Content In Sand

Determination Of Dry Density Of Soil Core Cutter Method

Procedure For Determination Of Aggregate Crushing Value

Procedure For Slump Test For Concrete

Determination Of Water Absorption Coarse Aggregate Format

Initial And Final Setting Test Of Cement Format

Concrete Quantite Register Grade Wise Summary Format

Procedure For Determination Of Water Content In Soil

Procedure For Determination Of Elongation Index Of Coarse Aggregate

Aggregate Crushing Value Test Format

Water Test Report Register Format

Testing Of Cement Testing Of Cement Field Test

Procedure For Sieve Analysis Of Fine Aggregates

Compressive Strength Test Of Bricks Format

Efflorescence Status Of Bricks Format

Procedure For Determination Of Flakiness Index Of Coarse Aggregate

Sieve Analysis For Coarse Aggregate Format

Procedure For Determination Standard Consistency Of Cement

Method Of Sampling Of Cement

Verification Of Compression Testing Machine Oil Leakage

Rolling Margin Register Format

Determination Of Specific Geavity Fine Aggregate Format

Concrete Quantity Register Pouring Details Format

Procedure For Sieve Analysis Of Coarse Aggregates

Verification Of Cube Moulds

Dimension Test Of Bricks Format

Slump Ans Temp Register For Concrete Format

Procedure For Filling Cubes

Consistency Of Standared Cement Paste Format

Rolling Margin Register Total Quantity Format

Procedure For Determination Of Aggregate Impact Value

Determination Of Specific Gravity And Water Absorption Of Fine Aggregates

Procedure For Compressive Strength Testing For Concrete

Incoming Material Receiving Register Format

Determination Of Specific Gravity And Water Absorption Of Coarse Aggregate

Internal Qa And Qc Audit Observation Format

Verification Of Sieves

Verification Of Mechanical Weigh Balance

Determination Of Water Absorption Of Bricks

List Of Site Laboratory Equipment

Flakiness Index Of Coarse Aggregate Format

Determination Of Efflorescence Of Bricks

Determination Of Specific Gravity Coarse Aggregate Format

Procedure For Determination Fineness Of Cement

Concrete Cube Register Format

Concrete Quantity Register Month Wise Summary Format

Water Absorption Test Of Bricks Format

Moisture Correction Format

List Of Records To Be Maintained Qc Qa

Fineness Test Of Cement Format

Procedure For Determination Compressive Strength Test Of Cement

Aggregate Impact Value Test Format

Elongation Index Of Coarse Aggregate Format

Procedure For Determination Of Compressive Strength Of Bricks

Material Test Plan Civil Works

Soundness Test Of Cement Format

Procedure For Determination Setting Time Of Cement

Fineness Test Of Flyash Format

Field Dry Density Of Soil By Core Cutter Method Format

Bend And Reband Test Of Steel Format

Determination Of Water Absorption Fine Aggregate Format

Compressive Strength Test Of Cement Format

Sieve Analysis For Fine Aggregate Format

Verification Of Pan Balance

Calibration Plan

IS Codes for landscape developement and IS Codes for approaches to sustainability

IS Codes for steel and its alloys

IS Codes for stones

is-codes-for-structural-sections

IS Codes for threaded fasteners rivets and nails

IS Codes for timber bamboo and other lignocellulosic building materrials

IS Codes for waterproofing and damp proofing materials

IS Codes for building chemicals

IS Codes for building lime & products

IS Codes for clay & stabilized soil products

IS Codes for doors windows & ventilators

IS Codes for floor covering roofing & other finishes

IS Codes for glass & mortar

IS Codes for paints and allied products

IS Codes for polymers plastics & geosynthetics geotextiles

IS Codes gypsum based materials

IS Codes Safety and IS Codes For Demolition and Dismantling

IS Codes for Roofing

IS Codes for Steel Work

IS Codes for Finishing

IS Codes for Flooring

IS Codes for Stone Work

IS Codes for Wood Work

IS Codes for Brick Work

IS Codes for RCC Work

IS Codes for ConcreteWork

IS Codes for Mortar

IS Codes for composite matrix products

IS Codes for cement & concrete

IS Codes for builder's hardware

IS Codes for aluminium & other light metals & their alloys

Quality Control (QC), Quality Assurance (QA), Quality Control Utilizes Tools and techniques

Quality Assurance manual (QAM), Quality Assurance Plan (QAP)

Quality Audits, Quality Assurance Formulations

Quality Control Method Statement, Pre- Construction Stage, Construction Stage, Post- Construction Stage

Quality Control Plan, Quality Control System, Quality control of materials, Quality control of workers, Quality control of execution

IS Codes for air conditioning heating and mechanical ventilation

IS Codes for drainage and sanitation

IS Codes for electrical and allied installations

is codes for firefighting and life safety

IS Codes for lighting and natural ventilation

IS Codes for solid waste management and IS Codes for gas supply

is codes for thermal insulation materials

IS Codes for water supply

is codes for welding electrodes and wires

IS Codes for electrical wiring fittings and accessories

IS Codes for conductors & cables

IS Codes for sanitary appliances and water fittings

Sponsored

PD Consulting Engineers Pvt. Ltd. Transforming construction for a new generation "Cost, Quality & Project management"

QS & Cost management, Bill Checking / Audit, Technical Auditors, Valuation, Contract and Tendering, Project Management, Project Planning, Quality Control, Consulting Engineers, Structural Consultancy

Close